ELECTRICITY MARKET

A

Initial Collateral

• The initial collateral amount to be used in calculating the total collateral required to be provided by market participants holding supply, aggregator, distribution, and transmission licenses has been set at 1,500,000 TRY.
• The initial collateral amount to be used in calculating the total collateral required from market participants holding generation licenses or Organized Industrial Zone (OIZ) generation licenses has been set at 1,500 TRY per MW of operational capacity, with a minimum of 100,000 TRY and a maximum of 1,500,000 TRY.

In case of a change in the installed capacity of a market participant in the business, the initial collateral required from the relevant market participant is recalculated according to the current installed power value.