Final Day Ahead Generation Schedule (FGS)
- FDGS’s are submitted on the basis of settlement aggregation entities for generation units.
- FDGS’s must be submitted after the completion of Day Ahead Market process between 14:00-16:00 one day before the relevant delivery day.
- FDGS’ are announced for 24 hours on the basis of settlement period. (In the current application hourly basis)