The Prices for electricity power plant based on renewable energy sources with RES Certificate to be in commissioning from 01.07.2021 date until 31.12.2025.
In according to with no 3453 presidential decision published in Official Gazette date 30 Jan 2021 no 31380 The Prices for electricity power plant based on renewable energy sources with RES certificate to be in commissioning from 01.07.2021 date until 31.12.2025 date as below.
Regards,
Renewable Energy Source Type | 2023-1.Quarter RESM Price (TL kr/kWh) | 2023-1.Quarter RESM Domestic Component Support Price (TL kr/kWh) | 01/04/2023 RESM Price (TL kr/kWh) | 01/04/2023 RESM Domestic Component Support Price (TL kr/kWh) |
---|---|---|---|---|
Hydro | 101,06 | 20,21 | 107,91 | 21,58 |
Wind | 80,86 | 20,21 | 86,34 | 21,58 |
Geothermal | 136,43 | 20,21 | 145,68 | 21,58 |
Landfill Gas | 80,86 | 20,21 | 86,34 | 21,58 |
Biomethanization | 136,43 | 20,21 | 145,68 | 21,58 |
Thermal Disposal | 126,33 | 20,21 | 145,68 | 21,58 |
Solar | 80,86 | 20,21 | 86,34 | 21,58 |